Poetry Designs

Milestone Tracking

Sunrise Villa - PLOT-2024-045

Overall Progress
Project Completion43%

Completed

3

In Progress

1

Pending

3

Design Approval

Completed

Assigned to: Sarah Johnson

Started:Jan 15, 2024
Completed:Jan 20, 2024
Target:Jan 20, 2024

All designs approved by client. Minor revisions completed.

Site Preparation

Completed

Assigned to: John Doe

Started:Jan 22, 2024
Completed:Feb 5, 2024
Target:Feb 5, 2024

Site cleared and leveled. Temporary structures erected.

Foundation Work

Completed

Assigned to: John Doe

Started:Feb 6, 2024
Completed:Mar 15, 2024
Target:Mar 15, 2024

Foundation completed as per structural drawings.

Structural Construction

In Progress

Assigned to: John Doe

Progress65%
Started:Mar 16, 2024
Target:Aug 30, 2024

Second floor slab casting in progress. On schedule.

MEP Installation

Pending

Assigned to: Mike Chen

Target:Oct 15, 2024

Awaiting structural completion.

Finishing Work

Pending

Assigned to: Sarah Johnson

Target:Nov 30, 2024

Pending MEP completion.

Final Handover

Pending

Assigned to: John Doe

Target:Dec 30, 2024