Overall Progress
Project Completion43%
Completed
3
In Progress
1
Pending
3
Design Approval
CompletedAssigned to: Sarah Johnson
Started:Jan 15, 2024
Completed:Jan 20, 2024
Target:Jan 20, 2024
All designs approved by client. Minor revisions completed.
Site Preparation
CompletedAssigned to: John Doe
Started:Jan 22, 2024
Completed:Feb 5, 2024
Target:Feb 5, 2024
Site cleared and leveled. Temporary structures erected.
Foundation Work
CompletedAssigned to: John Doe
Started:Feb 6, 2024
Completed:Mar 15, 2024
Target:Mar 15, 2024
Foundation completed as per structural drawings.
Structural Construction
In ProgressAssigned to: John Doe
Progress65%
Started:Mar 16, 2024
Target:Aug 30, 2024
Second floor slab casting in progress. On schedule.
MEP Installation
PendingAssigned to: Mike Chen
Target:Oct 15, 2024
Awaiting structural completion.
Finishing Work
PendingAssigned to: Sarah Johnson
Target:Nov 30, 2024
Pending MEP completion.
Final Handover
PendingAssigned to: John Doe
Target:Dec 30, 2024