Milestones & Phases

Filter by status:

Excavation & Site Preparation

ExcavationCompleted
Block ARajesh Kumar2024-12-15 to 2025-01-05
100%
3/3 subtasks
Started: 2024-12-15

Foundation Work - Block A

FoundationIn Progress
Block ARajesh Kumar2025-01-05 to 2025-01-20
75%
4/5 subtasks
Started: 2025-01-05

Superstructure - Block B Floor 1

SuperstructureIn Progress
Block B - Floor 1Suresh Patel2025-01-10 to 2025-02-05
45%
3/6 subtasks
Started: 2025-01-10

MEP Installation - Block A

MEPBlocked
Block A - Floor 1Amit Singh2025-01-20 to 2025-02-10
0%
0/8 subtasks
Not yet started

Masonry Work - Block A Floor 2

MasonryIn Progress
Block A - Floor 2Amit Singh2025-01-15 to 2025-02-10
30%
1/4 subtasks
Started: 2025-01-16

Finishing Work - Block A Floor 1

FinishingNot Started
Block A - Floor 1Priya Sharma2025-02-15 to 2025-03-10
0%
0/7 subtasks
Not yet started