Rock Formation Discovered During Excavation

HighUnder Review

Large rock formation found at 6ft depth blocking foundation work

Block A - Grid D3Rajesh Kumar2025-01-12
3 photos2 commentsDRG-ST-001-R2

Column Position Clash with MEP

CriticalOpen

Structural column interferes with MEP duct routing as per approved drawings

Block B - Floor 1 - Grid A2Suresh Patel2025-01-15
2 photos5 commentsDRG-AR-105-R3

Waterproofing Material Quality Issue

MediumResolved

Supplied waterproofing membrane does not match specification

Block A - BasementAmit Singh2025-01-14
4 photos3 comments

Drawing Dependency Tracking

2 open issues have triggered design revision requests. Track their status in the Design Management module.